What does the term "Lowest Bid Aware" refer to?

Prepare for the GFOA Certified Public Finance Officer Exam with focused study materials and detailed multiple-choice questions. Maximize your learning opportunities and enhance your understanding of capital and operating budgeting.

The term "Lowest Bid Aware" typically refers to a process that integrates a construction manager into the project before the final design is completed. In this method, a construction manager collaborates closely with the design team, allowing for a more streamlined approach to construction management. This inclusion helps in mitigating potential issues that could arise during the bidding or construction phases, as the construction manager can provide input on the feasibility and cost-effectiveness of design choices.

By engaging a construction manager early in the design process, there is an opportunity to assess construction methods, materials, and timelines, which can enhance project delivery and efficiency. This approach aligns with best practices in public finance and project management, where cost control, schedule adherence, and quality assurance are vital considerations.

In contrast, the other options refer to different methodologies that do not specifically capture the essence of involving a construction manager early in the project lifecycle. For example, merely selecting the lowest bid does not take into account quality or collaborative construction planning, while a focus on local contractors or a quality-based selection process diverges from the primary focus of integrating construction management at the design stage.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy